WARBY PARKER/HARRY'S
 
30,000 SF
 
Architect: 

TPG Architecture

Milestone/All Building Construction was originally  commissioned as the general contractor to build out the 8th floor for this growing eyeglass retailer, Warby Parker.  However, the client subsequently decided to sublease the space to Harry’s, which is a shaving company for men, during mid-construction.

 

The project entailed building out the space into a working environment. This included creating partitioned office spaces with glass walls, high end millwork, product display area and open work stations. The project also entailed building out a pantry, restrooms and conference areas.  All Building was also responsible for installation of all HVAC equipment, electrical components and exposed ductwork.

 

All Building halted construction to allow the architect to redesign for the new subtenants needs.  Once revised drawings were approved, the project team and subcontractors remobilized the complete project within the client’s tight timeframe.